During planning we soon noticed that building over a workshop is extremely complex – if conventional techniques are used. Factory halls in particular are almost never built over. But if building land is a scarce and precious resource and you want to keep room for later extensions, you have to build upwards. For this to be economically viable as well, new ways of thinking are needed. Structural engineers and structural designers have to reach a little deeper into their bag of tricks.
Besides the costs, there are other critical points:
- Ground conditions: How are the loads transferred into the ground? With the existing soil conditions, this is a particular challenge. Everything that is not piled will settle. This is why, for example, all underground pipes have to be “hung” from the base slab
- Imposed loads: Which imposed loads are actually necessary? For offices this is clear, but for workshop areas in special-purpose machine building it takes a look into the crystal ball
- Vibrations: The effect of vibrations arising in production and assembly (crane, machines) on the floors above
- Underground car park: Despite the great willingness to cycle to work, parking spaces are required. For parking, the ground surface would still be the cheapest option. An underground car park also has a significant influence on the structure, however. With a clever design, the structure above is supported and the cost disadvantages are partly offset. The underground car park must, however, be built uncompromisingly in waterproof (WU) concrete.
- Access roads: Loading ramps use up a lot of ground area. With a well-thought-out design of the access roads, they can be dispensed with. The future settlement of the outdoor areas is absorbed by massive, piled approach slabs.
From automation technology we know the series effect very well. We know that costs fall for repeating elements. We applied this approach to our building. The entire building is based on a uniform column grid. All heights are uniform. Functions that every floor needs are arranged strictly above one another. The building is therefore designed from the inside out, following the principle that form follows function.
In the building envelope, the windows in particular play a very important role and there are endless details to solve. Reveals, window sills, seals, and so on. If you consider windows, façade and shading as a single unit, very interesting series effects result. With a little brainpower and courage, the series concept can be implemented well, and the elements developed can even be fully prefabricated. Quality thus rises without costs rising.
The series concept can even be taken further for a future expansion of the business. By drawing up a development concept for the entire plot, you get an overview of how, for example, the crane runway could be extended or how the full build-out of the underground car park with the necessary ramps could work. Dividing it into implementation phases afterwards is then a simpler exercise.
It is worth considering which structural preparations are needed so that a base slab can later be connected directly. In our case, the building including the underground car park can simply be mirrored and thus doubled. The foundations are prepared in the connection area for this “series production”.